The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
Week of May 29th
Piping installation to continue in Chute, Boulden, Ruminant Animal Centre, Langille buildings and start in Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley and Jenkins Hall Buildings.
Electrical work to begin in Haley building. (Chance of minor noise with this work, hammer drilling)
Week of June 5th
Piping installation to continue in Langille, Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley, and Jenkins Hall Buildings.
Electrical work to continue in Haley building. (Chance of minor noise with this work, hammer drilling)
Any questions or concerns please contact:
Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca
Recent News
- Mia’s Lifelong passion for animals drives her journey to become a large animal veterinarian
- Blades, Blazes and Books: How Ben Fraser found his fire
- Students from Romblon State University (Philippines) on Campus
- Jenkins Hall ‑ Open for drop in meals
- Myles Sweet turns a family legacy and global experience into a promising career in artisanal cheesemaking
- 2025 DPMG Conference
- Excellence Recognized at 2025 Faculty of Agriculture Awards
- Truro Pride Parade ‑ Float participation